Al Khoory Executive Hotel

01 HVAC

Project Description

Project Description

Hotel Renovation Works – Addition of 10 TR.

 

Project Achievement

Client Approached us to install 10 TR DX Ducted Split system.

 

We advised them to connect 10TR to existing chilled water network, but client is afraid that it may affect the cooling of existing AC units in room. But after detail study of the project, we assured them that there will no effect on existing system even after addition of 10TR for which client agreed reluctantly with many conditions

 

We had successfully added 10TR to existing chilled water network and peak summer passed away without having impact on existing system.

 


Project Details

Property Type

Size

Year Built

Hotel